Project Insights
Dashboard
Projects
Timeline
Resources
Reports
Auth off
← Back to project
Edit Status Update — April 2026
1.DeliverHealth Interfaces
Reporting Period
Progress (%)
Scope
—
Red
Yellow
Green
Schedule
—
Red
Yellow
Green
Budget
—
Red
Yellow
Green
Root Cause (if Yellow / Red)
—
3rd Party
3rd Party Vendor
Analytics Resource
Analytics Resource Constraint
Funding
IT Resource
IT Resource Constraint
Legal / Contract
Other Resources Constraint
Scope Creek
Time Estimate to Complete
Mitigation Plan / Solution
Finalize Cerner Contracts
Stakeholder Value
Shareholder Value
KPIs
Monthly Update Notes
DeliverHealth SIU Filter configured for interim solution to share clinic visits and surgery schedules with providers who are enrolled in DeliverHealth. Was planning to push interface work till q3 due to capacity. In review of capital costs it was identified as denied in capital expenses. On hold for now until Heather Clinton & Tara Wisdom can figure it out.
Start Date
End Date
Save changes
Cancel