2. Microsoft 365 Conversion Assessment (2)

Fox Valley · MGP

Overview

Department
IT
Strategic Imperative
Expansion
Sponsor / Owner
John Bring
Project Manager
Tom Simmons
Ideal Team
Preferred Sprint
Priority
1. Mission Critical
Priority Payoff
Core Process
Core Process Category
% Complete
Resources
IT

Objective & KPI

Objective
Move Fox Valley from Google to Microsoft 365
Goal / Output
KPI
Notes

Financial Impact

2026 Op. (Exp.)
2026 Op. (Act.)
2026 Cap. (Exp.)
2026 Cap. (Act.)
2027 Op. (Exp.)
2027 Cap. (Exp.)
Capital Priority
Confidence

Dependencies

Depends on (upstream)

No prerequisites recorded.

Blocks / feeds (downstream)

Nothing waiting on this project.

Add dependency

Status History (3)

PeriodScopeScheduleBudgetProgressRoot CauseNotesActions
June 2026(edited)GreenGreenYellow80%• NOTES: Reached major milestone with phase 1 migration. 20 users have been setup on Sequel Ortho tenant and are successfully logged in. Still targeting June 1st for full migration. Budget is yellow as we have engaged HBS for training session and an additional PM was brought in. • PROJECT RISKS & RECOMMENDATIONS: Change control hurdles related to e-mail functions and use. Three year retention policy is not going over well. We need to determine if extending the three years is accomodating personal wants or clinical needs. If Google is needed from and IME or clinical content needs perspective, we will need to get legal involved to determine path forward. How long do we need to keep IME data. May need to look at legacy archival tool. • LEADERSHIP DISCUSSION NEEDED: (Yes / No) Duscissions are being had with Brandon & ChrisEdit
May 2026(edited)GreenYellowYellow55%Reached major milestone with phase 1 migration. 20 users have been setup on Sequel Ortho tenant and are successfully logged in. Still targeting June 1st for full migration.Edit
April 2026(edited)GreenYellowYellow55%Assessment is completed. Kicked off technical work with CDW vendor. FVO IT struggling to balance multiple projects and provide deliverables requested such as current state documentation which will be used to design the future state. Anticipate an additional resource being needed for sharepoint and intranet design. Also considering adding a contracted PMEdit