← Back to inventory
1. PMMC Contract Management - ACTIVE
Sequel Ortho · MGP
Overview
- Department
- PFS - 7600
- Strategic Imperative
- Operational Excellence & Quality
- Sponsor / Owner
- Heather Clinton
- Project Manager
- Drew Feuerbach
- Ideal Team
- TBD
- Preferred Sprint
- —
- Priority
- 1. Mission Critical
- Priority Payoff
- —
- Core Process
- —
- Core Process Category
- —
- % Complete
- —
- Resources
- Analytics
Objective & KPI
- Objective
- —
- Goal / Output
- —
- KPI
- —
- Notes
- —
Financial Impact
- 2026 Op. (Exp.)
- —
- 2026 Op. (Act.)
- —
- 2026 Cap. (Exp.)
- —
- 2026 Cap. (Act.)
- —
- 2027 Op. (Exp.)
- —
- 2027 Cap. (Exp.)
- —
- Capital Priority
- —
- Confidence
- —
Dependencies
Depends on (upstream)
No prerequisites recorded.
Blocks / feeds (downstream)
Nothing waiting on this project.
Status History (3)
| Period | Scope | Schedule | Budget | Progress | Root Cause | Notes | Actions |
|---|---|---|---|---|---|---|---|
| June 2026(edited) | Green | Yellow | Green | 88% | 3rd Party Vendor | Successes – Contracts are good to go, just pending data. Successes – Majority of data is completed Success - Meeting with account to discuss discounts on invoices due to additional work needed from our side. • PROJECT RISKS & RECOMMENDATIONS: • LEADERSHIP DISCUSSION NEEDED: (Yes / No) No | Edit |
| May 2026(edited) | Green | Yellow | Green | 88% | 3rd Party | Successes – Contracts are good to go, just pending data. Successes – Majority of data is completed Success - Meeting with account to discuss discounts on invoices due to additional work needed from our side. | Edit |
| April 2026(edited) | Green | Red | Green | 85% | 3rd Party | Successes – Contracts are good to go, just pending data. Successes – Majority of data is completed Meeting with account to discuss discounts on invoices due to additional work needed from our side. | Edit |
Archive & Remove
Hides it from active views; fully reversible. Use this for canceled or on-hold work.